First industrial scale carbon capture for lime production integrated with transport of CO2 to coastal hub and shipping to geological storage in the North Sea
The CalCC project aims to decarbonize the lime industry by capturing and storing CO2 emissions at Lhoist's Réty site, achieving 87% greenhouse gas emission avoidance through innovative Cryocap™ technology.
Projectdetails
Introduction
The CalCC project will showcase a pathway for decarbonisation in the lime industry. The project is capturing and permanently storing CO2 emitted during lime production at Lhoist Group’s Réty site.
Project Overview
This innovative project will cover the full CO2 value chain:
- Capture
- Pipeline transport
- Liquefaction
- Shipping
- Offshore geological storage
Carbon Capture Technology
For the carbon capture aspect of the project, Air Liquide will build the first Cryocap™ FG unit in a lime plant at industrial scale. The Cryocap™ technology uses cryogenic temperatures to separate gases and creates a 99.99% pure CO2 stream needed for CO2 transport and geological storage.
Environmental Impact
The project plans on achieving 87% relative greenhouse gas emission avoidance compared to the reference scenario.
Financiële details & Tijdlijn
Financiële details
Subsidiebedrag | € 125.198.197 |
Totale projectbegroting | € 125.198.197 |
Tijdlijn
Startdatum | 1-1-2023 |
Einddatum | 31-3-2039 |
Subsidiejaar | 2023 |
Partners & Locaties
Projectpartners
- Chaux et Dolomies du Boulonnaispenvoerder
- AIR LIQUIDE FRANCE INDUSTRIE
- AIR LIQUIDE GLOBAL E&C SOLUTIONS FRANCE
Land(en)
Vergelijkbare projecten binnen Innovation Fund
Project | Regeling | Bedrag | Jaar | Actie |
---|---|---|---|---|
Bio-Energy Carbon Capture and Storage (BECCS) at the existing Combined Heat and Power-plant KVV8 at Värtaverket, Stockholm, SwedenThe Beccs Stockholm project aims to establish a full-scale BECCS facility to capture and store CO2, achieving 7.0 Mt CO2e removals while enhancing renewable energy efficiency. | InnovFund LSC | € 180.000.000 | 2021 | Details |
Coda by Carbfix - a highly scalable, cost effective CO2 mineral storage hubCoda Terminal aims to be the first carbon mineral storage facility, utilizing sustainable shipping to permanently store CO2 in Iceland, significantly aiding EU climate goals. | InnovFund LSC | € 115.000.000 | 2023 | Details |
FUse, REuse,ReCycleThe FUREC project converts non-recyclable waste into 54,000 tonnes of hydrogen annually, supplying the chemical industry while achieving a 101% reduction in greenhouse gas emissions. | InnovFund LSC | € 108.000.000 | 2023 | Details |
Reduction of CO2 emissions in methanol production from municipal non-recyclable wasteThe ECOPLANTA project aims to transform non-recyclable municipal waste into 237 kt/y of methanol, reducing GHG emissions by 3.4 Mt CO2eq over ten years while displacing fossil fuels. | InnovFund LSC | € 106.379.783 | 2021 | Details |
Bio-Energy Carbon Capture and Storage (BECCS) at the existing Combined Heat and Power-plant KVV8 at Värtaverket, Stockholm, Sweden
The Beccs Stockholm project aims to establish a full-scale BECCS facility to capture and store CO2, achieving 7.0 Mt CO2e removals while enhancing renewable energy efficiency.
Coda by Carbfix - a highly scalable, cost effective CO2 mineral storage hub
Coda Terminal aims to be the first carbon mineral storage facility, utilizing sustainable shipping to permanently store CO2 in Iceland, significantly aiding EU climate goals.
FUse, REuse,ReCycle
The FUREC project converts non-recyclable waste into 54,000 tonnes of hydrogen annually, supplying the chemical industry while achieving a 101% reduction in greenhouse gas emissions.
Reduction of CO2 emissions in methanol production from municipal non-recyclable waste
The ECOPLANTA project aims to transform non-recyclable municipal waste into 237 kt/y of methanol, reducing GHG emissions by 3.4 Mt CO2eq over ten years while displacing fossil fuels.
Vergelijkbare projecten uit andere regelingen
Project | Regeling | Bedrag | Jaar | Actie |
---|---|---|---|---|
Silverstone: Full-scale CO2 capture and mineral storage at the Hellisheidi power stationProject Silverstone aims to achieve near-zero carbon emissions by using Carbfix technology for permanent CO2 capture and mineral storage at a geothermal power plant in Iceland. | InnovFund SSC | € 3.867.988 | 2021 | Details |
Cement-free building products with negative carbon footprints by using CO2 gas and by-product from respectively Lime and stainless steel plantsThe CO2ncrEAT project aims to decarbonize the European construction sector by producing carbon-negative masonry blocks using recycled materials and captured CO2, significantly reducing greenhouse gas emissions. | InnovFund SSC | € 4.265.135 | 2023 | Details |
EcoCaptureHet project ontwikkelt en test een innovatieve techniek voor het afvangen van CO2 uit de atmosfeer om klimaatverandering te bestrijden. | OP Oost - Onderzoek en Innovatie | € 275.922 | 2024 | Details |
Silverstone: Full-scale CO2 capture and mineral storage at the Hellisheidi power station
Project Silverstone aims to achieve near-zero carbon emissions by using Carbfix technology for permanent CO2 capture and mineral storage at a geothermal power plant in Iceland.
Cement-free building products with negative carbon footprints by using CO2 gas and by-product from respectively Lime and stainless steel plants
The CO2ncrEAT project aims to decarbonize the European construction sector by producing carbon-negative masonry blocks using recycled materials and captured CO2, significantly reducing greenhouse gas emissions.
EcoCapture
Het project ontwikkelt en test een innovatieve techniek voor het afvangen van CO2 uit de atmosfeer om klimaatverandering te bestrijden.