Green H2 Project of ZE PAK SA envisages the construction of the first green hydrogen production installation for transportation purposes in Poland. The installation is planned to be built up sequentially, with the first phase targeted at 5MW power, gradually increasing up to 50MW depending on the dynamics of the future growth of the market.

Electrolysis System

The electrolysis system will consist of:

  1. 2 electrolyzers powered by own renewable sources (60% of electric energy consumption).
  2. Market-sourced Power Purchase Agreements (PPAs) with suppliers of renewable power (40%).

The main innovative component introduced by ZE PAK SA is the construction of a self-designed electrolyzer stack. The final prototype is planned to allow for:

  • 15% CAPEX savings.
  • 5% energy efficiency increase in comparison to available technologies.

Target Market

The entire H2 production volume of the installation will be destined for use within the transportation sector, which is the company's main strategic direction in terms of H2 development. ZE PAK SA's primary target market in the short term consists of fueling self-produced H2 public buses.

Additionally, an extra revenue stream (15% of overall revenues) of the installation will consist of sales of oxygen, which is a byproduct of the electrolysis process.

Environmental Impact

With net emission generation per annum equal to 364 tonnes of CO2 and expected production volume at 710 tonnes of hydrogen, the GHG emissions per unit of hydrogen are calculated at the level of 0.51 tCO2 equivalent / t H2. This is significantly below both the EU ETS benchmark value (8.85 tCO2 / tH2) as well as the average value for the 10% most efficient installations.

Project Timeline

Project works have started in 2020. All feasibility, preparatory, permitting, and construction works are planned to be completed in 1Q 2024. The entry into operations is planned for the 1st of June 2024.

ZE PAK SA has already covered part of the costs of the project (2.1 mEUR; not included in the budget of the application to IF), which reflects the company's strong commitment to successfully launching the project.

Financiële details & Tijdlijn

Financiële details

Subsidiebedrag€ 4.460.000
Totale projectbegroting€ 4.460.000

Tijdlijn

Startdatum1-10-2021
Einddatum31-12-2028
Subsidiejaar2021

Partners & Locaties

Projectpartners

  • PAK PCE BIOPALIWA I WODOR SPOLKA ZOGRANICZONA ODPOWIEDZIALNOSCIApenvoerder
  • ZE PAK SPOLKA AKCYJNA
  • EXION HYDROGEN POLSKIE ELEKTROLIZERY SPOLKA Z OGRANICZONA ODPOWIEDZIALNOSCIA
  • EXION HYDROGEN POLSKIE ELEKTROLIZERY SPOLKA Z OGRANICZONA ODPOWIEDZIALNOSCIA

Land(en)

Poland

Vergelijkbare projecten binnen Innovation Fund

Innovation F...

Small-scale green hydrogen production facility

The Green H2 project aims to produce green hydrogen via a 1 MW electrolyser powered by solar energy, reducing GHG emissions and enabling scalable, zero-emission hydrogen for various sectors.

€ 4.492.131
Innovation F...

Initiating the Production of Green Hydrogen for Transport and Other Applications in the Czech Republic

The VOZARTEK project aims to kick-start the green hydrogen market in the Moravian-Silesian Region by producing 270 tonnes annually using solar and biomass, reducing GHG emissions by 98%.

€ 4.470.000
Innovation F...

Green Hydrogen Project for Transport in Cyprus

The GreenH2CY project aims to produce green hydrogen from renewable energy for transport in Cyprus, reducing GHG emissions by 21,677 tonnes over ten years while supporting a hydrogen economy.

€ 4.499.877
Innovation F...

HydrOxy Hub Walsum

The HydrOxy Hub Walsum project aims to build a 157.2 MW PEM electrolyser in Germany to produce renewable hydrogen, enhancing decarbonization in steel and shipping while creating local jobs.

€ 49.212.730
Innovation F...

GREENH2ATLANTIC

The GreenH2Atlantic project aims to develop a 100 MW electrolyser in Portugal to produce renewable hydrogen, reduce GHG emissions, and create jobs while promoting a circular economy and energy transition.

€ 61.987.272

Vergelijkbare projecten uit andere regelingen

Demonstratie...

H2 Hollandia

Het H2 Hollandia-project demonstreert de haalbaarheid van een 5 MW PEM elektrolyser die 300 ton groene waterstof per jaar produceert uit overtollige zonne-energie, ter ondersteuning van de energietransitie.

€ 6.567.117
Demonstratie...

Power to Clean Gas

Het project ontwikkelt een kosteneffectief elektrolyser-systeem voor waterstofproductie uit overtollige groene stroom, gericht op de power-to-gas-markt met een prototype van 50kW.

€ 301.749
Demonstratie...

Groene waterstof in een flexibel elektriciteitssysteem

Het project ontwikkelt een Power-to-X systeem in Nieuwegein om overtollige zonne-energie om te zetten in groene waterstof en warmte, met als doel de efficiëntie en flexibiliteit van het elektriciteitssysteem te vergroten.

€ 446.000
Demonstratie...

Smart Hydrogen Hub: Een lokale groene waterstofketen in Rotterdam voor de industrie en mobiliteit

De Smart Hydrogen Hub demonstreert een innovatieve waterstofproductiefaciliteit in Rotterdam, gericht op CO2-reductie en het creëren van een positieve businesscase voor groene waterstof.

€ 6.354.380
EIC Accelerator

CO2-free, on-demand, on-site production of low-cost green hydrogen produced with micro-wave plasma

SAKOWIN aims to revolutionize hydrogen production by delivering cost-effective, CO2-free H2 from biomethane or NG, targeting €75M in revenue by 2030 through scalable equipment sales and licensing.

€ 2.500.000